Tool

Earned value calculator

Enter four figures at the same status date to get the standard earned value measures. The values loaded below are an invented example, not real project data.

Example figures loaded.

How these are calculated

MeasureFormula
Cost varianceEV − AC
Schedule varianceEV − PV
CPIEV ÷ AC
SPIEV ÷ PV
EAC (CPI method)BAC ÷ CPI
EAC (CPI × SPI method)AC + (BAC − EV) ÷ (CPI × SPI)
ETCEAC − AC
VACBAC − EAC
TCPI (to BAC)(BAC − EV) ÷ (BAC − AC)
Percent completeEV ÷ BAC

SPI is cost-based, so it drifts towards 1.0 as a project finishes, however late it is. Late in a project, look at time-based schedule measures as well. These formulas are standard, but check them against the method your organisation or contract specifies.

The status colours use simple bands: an index of 1.0 or better is on track, 0.95 to 1.0 is worth watching, below 0.95 needs attention. Your organisation's thresholds may differ.